Critical Chain
Project Management
(CCPM) | | |
Information
The resource buffer is information to the resources when they will be needed on the critical chain.
This substitutes for
fictional start and finish dates for each task. Your weekly project status meetings may fill this function,
if resource
managers participate. CCPM+ and some other critical chain software substitute a
prioritized task list by resource to replace this function.
|