Critical Chain Project Management (CCPM)

bullet1 Exploit
bullet2 Buffer Management

bullet3 Reporting

The Buffer Report enables project resources to determine which task to work on next, and provides thresholds for Project Manager action.

bullet4 Buffer Penetration

Buffer penetration is the difference between the initial planned and current estimate of the completion of the last task on the chain feeding the buffer, based on the estimate of remaining days for the task currently being worked.

bullet4 Action Thresholds

Establish action thresholds to plan and activate plans to recover project duration based on Project Buffer and Feeding Buffer penetration. The simple rule is action thresholds at 1/3 and 2/3 of buffer penetration. You may wish to use a dynamic threshold for the Project Buffer; i.e. thresholds that increase along the project duration.