Critical Chain Project Management (CCPM)

bullet1 Elevate
bullet2 Cost Buffer

bullet3 Variational (SSQ)

The variational element of the cost buffer is calculated the same way as the variational component of the Project Buffer. You can estimate it using the square root of the sum of the squares method (SSQ), the very similar PERT Cost method, or using Monte Carlo analysis.